Moving power HV towers without downtime

WORK SCOPE

  • Assignment/engineering concept
  • Lifting and moving 17 complete HV towers including conductors and fixtures
  • Scheduling and realisation of temporary access roads to the various pylon sites

RESULT

Using the existing HV towers as a temporary provision saved 50% on the scheduled downtime of the line, and the grid operator managed to have a two system provision available during the work in the winter.